Dear Bridges-2 Users,

The Bridges-2 migration is now expected to begin:

November 9, 2026

The system will be unavailable for approximately 4–6 weeks.

Key actions:

  • Complete data backups by: November 1, 2026
  • Avoid delaying transfers—bandwidth is shared
  • Ensure workloads do not extend into the outage

PSC cannot guarantee complete data integrity through the relocation. As a reminder, the Ocean filesystem is never backed up, so as a best practice, we strongly recommend our users maintain offsite backups of important data.

For full details, timelines, and preparation guidance, please visit: Bridges-2 Migration Information Page  

As always, if you have questions about the migration, your data, or workload planning, please contact the PSC Help Desk at help@psc.edu. We are happy to help you prepare.

Thank you,

Bridges-2 Team